Nov 17, 2008

Gravel, and Sand, and Compactors, Oh My!


Foundation cages completed, next comes the graveled trenches.
Category:Lesotho 2008/09 
Posted by: Ann
Today was a BIG day. We wired the last of the foundation cages. The grading of the site was finished. The exact building site was determined, measured and lined, and the footing trenches were dug. We took delivery of 3 trucks of gravel, one of sand and a compactor. Some gravel distribution into the footing trenches began. It was a 13 hour day, we're beat, and students, teachers and volunteers alike have big smiles on their faces.